Welding inspection failures cost far more than the welds themselves — rejected pressure vessels, structural connections that fail load testing, pipeline girth welds that require cut-out and repair, and AWS D1.1 nonconformances that ground a fabrication project until a Certified Welding Inspector signs off on corrective work. This checklist covers every inspection gate a CWI performs: pre-weld verification, in-process monitoring, visual examination, dimensional checks, and NDT hold points — structured to the requirements of AWS D1.1 Structural Welding Code and API 1104 Pipeline Welding Standard.
Digitize CWI Sign-Off, NDT Hold Points, and Weld Map Records — Every Joint Traceable from Fit-Up to Final Acceptance
iFactory's welding inspection module routes hold points to the CWI's tablet, captures digital sign-off with timestamp, links NDT reports to the weld joint record, and exports the complete weld package for AWS D1.1 and API 1104 documentation requirements.
Welding Procedure Specification (WPS) is approved, current, and available at the weld station for the joint configuration being welded
CWI Hold Point
Welder's qualification record (WQR/WPQ) is verified — qualified for the process, position, base metal, and thickness range being welded
CWI Hold Point
Base metal material is verified against the Material Test Report (MTR) — heat number, grade, and specification confirmed against the drawing requirement
Required
Joint fit-up dimensions verified: root opening, root face, bevel angle, and groove geometry match the WPS requirements and drawing tolerances
CWI Hold Point
Joint surfaces are clean — free of mill scale in the weld zone, paint, oil, moisture, rust, and other contaminants to the extent specified by the WPS
Required
Preheat temperature is measured and confirmed to meet WPS minimum — measured at least 3 inches (75mm) from the weld joint on the base metal
CWI Hold Point
Filler metal classification, lot number, and condition verified against WPS — flux is dry, electrodes are stored correctly, FCAW wire is undamaged
Required
Alignment and mismatch (hi-lo) of abutting pipe or plate edges is within specified tolerance before tack welding begins
Required
Tack welds are inspected for cracks before production welding covers them — cracked tack welds must be removed, not welded over
Required
Interpass temperature is monitored and does not exceed the WPS maximum — measured before depositing each subsequent pass on multi-pass welds
Required
Welding parameters — amperage, voltage, travel speed, and wire feed speed — are verified to be within the WPS essential variable ranges
Required
Root pass is visually examined before being covered by subsequent passes — root is fully fused with no cracks, excessive porosity, or burn-through
CWI Hold Point
Each pass is cleaned of slag before the next pass is deposited — interbead slag inclusions are not permitted and are removed before proceeding
Required
Welding sequence and direction follow the WPS or drawing requirement — distortion control practices are being applied where specified
Recommended
Shielding gas flow rate and coverage are verified at start of welding and after any interruption — for GMAW, FCAW-G, and GTAW processes
Required
Repairs to in-process defects are performed using an approved repair procedure — not by re-welding over defective areas without removal
CWI Hold Point
| Discontinuity | AWS D1.1 Visual Acceptance Criterion | API 1104 Visual Acceptance Criterion | Inspection Method |
|---|---|---|---|
| Cracks | Not permitted — any length, any location | Not permitted — any length, any location | Visual + MT or PT confirmation |
| Incomplete Fusion (surface) | Not permitted | Not permitted | Visual — look for visible lack of fusion at weld toe |
| Undercut — statically loaded | Max 1/32 inch (0.8mm) depth; max 1/8 inch (3mm) for secondary members | Max 1/32 inch (0.8mm) depth for external; varies by class for internal | Weld undercut gauge; visual confirmation |
| Undercut — cyclically loaded | Max 1/32 inch (0.8mm) for tension; none permitted in some categories | See API 1104 Table for applicable class | Weld gauge + lighting at low angle |
| Porosity (surface) | Max 3/8 inch (9.5mm) any pore; max 3/8 inch total in any linear inch | Scattered: max 1/4 inch (6mm) individual pore; see Sec. 9.3 for cluster | Visual; refer to RT if subsurface suspected |
| Weld Reinforcement (groove) | Max 1/8 inch (3mm) up to 1 inch thick; 3/16 inch for 1–2 inches; 1/4 inch over 2 inches | Max 1/16 inch (1.6mm) above flush on external; flush to 1/16 inch above base on internal | Weld reinforcement gauge |
| Underfill / Concavity | Not permitted on groove welds — weld must be flush or above base metal | Internal concavity: max 1/32 inch below flush of pipe OD | Weld gauge; straight edge across joint |
| Overlap (cold lap) | Not permitted | Not permitted | Visual — weld toe rolling over base metal without fusion |
| Arc Strikes | Not permitted on base metal outside weld area — must be removed by grinding | Not permitted — must be investigated for cracks | Visual full surface sweep; MT/PT on removal area |
| Weld Profile / Crown | Convexity limited per AWS D1.1 Table 6.1; smooth transition to base metal required | Crown height: 1/16 inch to 3/32 inch (1.6–2.4mm) for pipe girth welds | Weld profile gauge; visual at angle |
Visual examination is performed under adequate lighting — minimum 50 foot-candles (540 lux) at the examination surface per AWS D1.1 Clause 6.9
Required
Weld is examined from an angle not exceeding 30° to the weld surface — the CWI physically accesses all required viewing angles for the joint configuration
Required
Weld dimensions are measured with calibrated weld gauges — fillet weld leg size, throat dimension, reinforcement height, and undercut depth recorded
CWI Hold Point
All required weld length is present — intermittent weld spacing and minimum weld length requirements from the drawing are confirmed
Required
Weld is identified with the welder's stamp or identification mark as required by the WPS or fabrication procedure
Required
Radiographic Testing (RT) — technique, exposure, IQI placement, and film density confirmed per AWS D1.1 Annex E or API 1104 Section 11 before exposure
NDT Required
Ultrasonic Testing (UT) — instrument calibration to reference blocks, scanning pattern, and search unit confirmed per AWS D1.1 Annex F or applicable procedure
NDT Required
Magnetic Particle Testing (MT) — yoke or prod technique, coverage, and residual field check performed per AWS D1.1 Clause 6 or ASME procedures for the applicable material
NDT Required
Liquid Penetrant Testing (PT) — dwell time, developer application, and interpretation meet the requirements of ASME Section V Article 6 or equivalent standard for the applicable code
NDT Required
NDT is performed after any required post-weld heat treatment (PWHT) — not before — unless the code specifically permits pre-PWHT NDT for the applicable joint type
CWI Hold Point
All NDT reports are reviewed and accepted by the CWI before the joint is accepted — NDT technician signature, date, and Level II certification number are on every report
CWI Hold Point
Weld map or weld joint register identifies every weld joint on the structure or pipeline with a unique joint number traceable to the drawing revision
Required
Each weld joint record includes: WPS used, welder ID, date welded, preheat temperature, filler metal heat number, visual examination result, and CWI sign-off
Required
All NDT reports are referenced in the joint record with report number, method, date, technician level, and accept/reject disposition noted
Required
Weld repair records document: joint number, original defect type and location, repair procedure used, re-inspection method, and final acceptance disposition
Required
PWHT charts and time-temperature records are attached to the joint record for every joint requiring post-weld heat treatment per the WPS or code
Required
Completed weld package — all records, NDT reports, MTRs, WPS, WQRs, and repair records — is reviewed by the CWI and signed as complete before turnover to the owner or next construction phase
CWI Hold Point
Replace Paper Weld Books With Digital Joint Records — CWI Sign-Off, NDT Links, and Weld Map Traceability Built In
iFactory's welding inspection module creates a digital weld joint record for every joint on your weld map — with CWI hold point routing, NDT report attachment, repair record tracking, and one-click package export for AWS D1.1 and API 1104 documentation turnover.
Frequently Asked Questions — Welding Inspection
What is the difference between AWS D1.1 and API 1104 acceptance criteria?
AWS D1.1 is the Structural Welding Code for steel — it applies to buildings, bridges, offshore platforms, and fabricated structures. API 1104 is the Pipeline Welding Standard, written specifically for onshore and offshore pipeline girth welds. Their acceptance criteria differ significantly: API 1104 has stricter weld crown height limits, different porosity acceptance tables, and more detailed radiographic acceptance criteria organized by defect class. A weld acceptable under AWS D1.1 may not be acceptable under API 1104, and vice versa. Always confirm which code governs before applying acceptance criteria.
How long does welder qualification remain valid under AWS D1.1?
Under AWS D1.1 Clause 4.22, welder qualification remains in effect indefinitely unless: the welder has not used the process for which they are qualified for a period exceeding six months, there is specific reason to question the welder's ability, or the welder fails a subsequent performance qualification test. API 1104 Section 6.4 similarly specifies a six-month continuity requirement. Documentation of recent use must be maintained — a welder who claims to have used the process within six months must have production or test records to support that claim.
When is radiographic testing required versus ultrasonic testing?
AWS D1.1 allows RT or UT for most groove weld applications — the choice is often contractually specified or left to the Engineer. RT is better at detecting volumetric defects (porosity, slag inclusions) and provides a permanent visual record. UT is better at detecting planar defects (cracks, lack of fusion) that are parallel to the X-ray beam and may be missed by RT. For material thickness above 1-1/2 inches, UT is generally preferred for its superior sensitivity to planar defects in thick sections. API 1104 specifies RT as the primary method for pipeline girth weld acceptance but permits automated UT systems that have been demonstrated to provide equivalent sensitivity.
What happens when a weld is rejected — can it always be repaired?
AWS D1.1 Clause 5.26 permits repair of rejected welds using a qualified repair procedure. The defective area must be removed by grinding, air carbon arc gouging, or mechanical means — confirmed by MT or PT to be fully removed before re-welding. AWS D1.1 does not limit the number of repair attempts but requires Engineer approval for repairs beyond the first attempt on cyclically loaded structures. API 1104 Section 9.7 limits pipe girth weld repairs: a second repair attempt on the same area requires special authorization. Cut-out (removal of the entire joint and re-welding) is required for certain crack types and for joints that have failed multiple repair attempts.