Rotating Equipment Overhaul During Turnarounds

By Johnson on July 30, 2026

rotating-equipment-overhaul-turnaround-planning

Rotating equipment overhauls represent the single largest driver of turnaround duration variability in oil and gas facilities, yet they are frequently planned using generic templates that fail to account for the specific condition, complexity, and vendor dependencies unique to each machine. A centrifugal compressor overhaul at one refinery might require 14 days with an OEM shop visit, while an identical machine at another facility with a well-managed spare rotor program could complete the same scope in 8 days using a local certified shop. The difference is not luck but planning discipline applied systematically to scope definition, vendor logistics, parts staging, and critical path management. Understanding how to structure rotating equipment overhaul planning as an integrated component of turnaround execution, rather than a standalone maintenance activity, determines whether your unit returns to service on schedule or faces weeks of delay driven by a single machine waiting on a vendor or a missing spare part. Book a demo to see how iFactory tracks rotating equipment overhaul progress within your turnaround command center.


Every Day Your Compressor Sits Disassembled Costs You a Million Dollars in Lost Production.

iFactory gives your turnaround team real-time visibility into every rotating equipment overhaul work stream, vendor status, and critical path dependency so you can compress schedules and eliminate waiting time.

Equipment Classification

Rotating Equipment Complexity Tiers Encountered During Turnarounds

Not all rotating equipment overhauls carry equal planning complexity or schedule risk. A large centrifugal compressor with a rotor that must leave site for OEM shop machining creates fundamentally different planning demands than a centrifugal pump that can be overhauled entirely in the field by site maintenance crews. The following classification groups the six most common rotating equipment types encountered in oil and gas turnarounds into complexity tiers based on the number of external dependencies, specialized vendor requirements, and critical path sensitivity they typically introduce. Understanding which tier each machine in your turnaround scope falls into determines the level of planning rigor, lead time, and contingency required.

Tier 1 - Critical
Centrifugal Compressor
Schedule Impact: 8-16 days
Rotor often requires OEM or certified shop machining
Spare rotor management determines critical path strategy
Multi-stage internal alignment with precision tolerances
Dry gas seal installation requires vendor specialist
Auxiliary systems including lube oil and seal gas add scope
Tier 1 - Critical
Gas Turbine Driver
Schedule Impact: 14-28 days
OEM service agreement typically mandatory for hot section work
Boroscope inspection findings can dramatically expand scope
Blade replacement lead times can exceed turnaround window
Control system calibration requires OEM software access
Combustion inspection vs hot section vs major overhaul decision
Tier 2 - High
Reciprocating Compressor
Schedule Impact: 6-14 days
Cylinder bore inspection and re-ring decision based on wear
Crankshaft deflection readings determine bearing scope
Valve plate overhaul can be done on-site or at vendor
Crosshead and wrist pin inspection requires specialized NDE
Multi-cylinder machines have parallel work stream opportunities
Tier 2 - High
Steam Turbine
Schedule Impact: 10-20 days
Blade root and shroud inspection drives scope expansion
Governor and trip system testing requires specialist
Shell joint re-machining may require field machining vendor
Labyrinth seal replacement scope determined at opening
Coupling to driven equipment adds alignment dependency
Tier 3 - Moderate
Large Centrifugal Pump
Schedule Impact: 3-7 days
Impeller and casing wear ring measurement at opening
Mechanical seal replacement with vendor field support
Bearing replacement typically straightforward with spares
Shaft runout check determines need for shop repair
Most scope can be completed by site crews if parts available
Tier 3 - Moderate
Motor and Generator Sets
Schedule Impact: 3-8 days
Stator winding resistance and insulation testing at shutdown
Rotor pull may be required based on electrical test results
Bearing replacement and re-greasing straightforward
Vibration analysis baseline required before re-energization
Electrical contractor coordination for high-voltage testing

The critical insight from this classification is that Tier 1 equipment should trigger a dedicated overhaul planning workstream that begins 12 to 18 months before the turnaround, with its own scope development timeline, vendor procurement process, and risk register. Tier 2 equipment requires focused planning attention starting 9 to 12 months out. Tier 3 equipment can be planned within the standard turnaround planning timeline but still needs specific parts verification and work package development rather than generic pump overhaul templates.

Overhaul Lifecycle

Seven-Phase Overhaul Planning and Execution Lifecycle

A major rotating equipment overhaul during a turnaround follows a distinct lifecycle that begins long before the unit shuts down and extends well past mechanical completion. Each phase has specific deliverables, decision gates, and dependencies that must be managed as an integrated sequence. Skipping or compressing any phase transfers risk to the execution window where the cost of resolving planning gaps increases by a factor of 10 to 50 for every day of schedule delay. The following lifecycle represents the HFE-validated planning sequence used by top-quartile turnaround performers for Tier 1 and Tier 2 rotating equipment overhauls.

P1
Condition Assessment and Data Collection
T-18 to T-12 months
Collect vibration trend data, performance curves, and operating logs for the preceding 24 months. Schedule and execute focused on-stream inspections including boroscope examinations, thermographic surveys, and lube oil analysis review. Review manufacturer service bulletins and applicable regulatory inspection requirements. Document any operational upsets, surge events, or abnormal operating conditions that may have damaged internal components.
P2
Scope Definition and Overhaul Strategy
T-12 to T-9 months
Define the baseline overhaul scope based on condition assessment findings, manufacturer recommendations, and regulatory requirements. Make the critical strategic decision between full rotor shop overhaul with spare rotor exchange versus in-situ overhaul without rotor removal. For machines without spare rotors, evaluate the cost and lead time of procuring a spare rotor against the schedule risk of sending the only rotor off-site. Identify conditional scope items that will be confirmed or rejected based on findings at opening.
P3
Vendor Selection and Contracting
T-9 to T-6 months
Issue technical specifications to qualified OEM and third-party overhaul shops. Evaluate proposals based on technical capability, shop capacity during the planned window, quality system certifications, and historical performance on similar machines. Execute contracts with guaranteed shop duration, penalty clauses for late delivery, and mandatory progress reporting milestones. For OEM-dependent work such as gas turbine hot section repairs, secure service slot commitments and confirm parts availability with firm delivery dates.
P4
Parts Procurement and Staging
T-6 to T-2 months
Order all long-lead replacement parts including bearings, seals, wear rings, and consumables. Verify spare rotor condition and arrange for pre-overhaul inspection at the vendor shop if a rotor exchange strategy is planned. Stage all materials in a dedicated laydown area with verified part numbers against the bill of materials. Identify any parts with delivery dates that overlap with the planned execution window and develop contingency plans including alternative suppliers or temporary substitutes.
P5
Work Package Development and Pre-Work
T-2 months to T-0
Develop detailed work packages with step-by-step procedures, torque specifications, clearance criteria, and quality hold points. Complete any pre-shutdown work that can reduce the execution scope including disconnecting auxiliary piping, removing casing insulation, and setting up scaffolding and rigging. Conduct pre-TAR safety reviews covering lift plans, confined space entries, hot work permits, and energy isolation requirements. Brief all execution crews on the critical path and the specific handoff points between mechanical, vendor, electrical, and instrumentation teams.
P6
Execution with Parallel Work Stream Management
T-0 to T+Duration
Execute disassembly, inspection, and reassembly activities while simultaneously managing vendor shop work on off-site components. Conduct opening inspections immediately upon access to confirm or reject conditional scope items. Hold daily coordination meetings between all parallel work streams to resolve conflicts over shared resources, crane time, and access to the machine. Track vendor shop progress through mandatory milestone reports and adjust the on-site schedule if vendor delivery dates shift. Execute all quality hold point inspections with documented evidence before proceeding past each checkpoint.
P7
Recommissioning and Performance Verification
T+Duration to T+Duration+7 days
Execute static checks including alignment verification, electrical megger testing, and control system functional testing. Conduct dynamic testing with progressively increasing speed and load while monitoring vibration, bearing temperatures, seal leakage, and process parameters at each stage. Compare actual performance curves against design curves and pre-overhaul baseline to verify that the overhaul restored the machine to acceptable operating condition. Document all test results and hand over the machine to operations with updated maintenance records, new baseline vibration data, and any recommended operating restrictions.
Scope Development

Overhaul Scope Categories by Decision Trigger

Effective scope development for rotating equipment overhauls requires categorizing every work item by the type of decision trigger that determines whether it is included in the final scope. This categorization is critical because it determines when the scope item can be confirmed, which in turn determines procurement timing, work package readiness, and resource allocation. Scope items confirmed too late create the same execution delays as discovery work in other turnaround disciplines. The following matrix shows the three scope categories, their decision triggers, confirmation timing, and typical work items for a large centrifugal compressor overhaul as a reference example.

Scope Category Decision Trigger Confirmation Timing Procurement Lead Time Typical Scope Items (Centrifugal Compressor Example)
Mandatory Scope Regulatory requirement, manufacturer recommendation at current run hours, or known degradation from condition monitoring Confirmed during P2 scope definition, T-12 to T-9 months Long-lead items ordered in P4, standard items in P4-P5 Bearing replacement, dry gas seal replacement, lube oil system flush, coupling inspection, alignment check, all clearance measurements, balance piston inspection
Conditional Scope Findings at opening inspection including visual damage, dimensional measurements, NDE results, or unexpected degradation Confirmed during P6 execution, typically within first 48-72 hours after machine opening Pre-procured contingency items staged on-site, emergency procurement for items not anticipated Impeller repair or replacement if erosion damage found, diaphragm re-machining if distortions exceed limits, casing joint re-facing if leakage detected, rotor replacement if shaft damage found
Discretionary Scope Planning team judgment based on risk assessment, remaining useful life analysis, or opportunity to upgrade during a scheduled outage Decided during P2 scope definition but can be added or removed during P4-P5 based on budget or schedule pressure Same as mandatory if included, not procured if excluded Impeller upgrade to newer aerodynamic design, control system modernization, bearing type upgrade from sleeve to magnetic, added instrumentation probes, casing modifications for future capacity increase

The most common planning failure in rotating equipment overhauls is treating conditional scope items as if they are optional extras rather than highly probable scope items that happen to require opening inspection for final confirmation. Experienced planners estimate conditional scope probability for each item and pre-procure high-probability items to avoid the 4-to-8-week delay that emergency procurement would cause if the condition is confirmed at opening. A conditional item with a 70 percent probability of being required should be treated as mandatory for procurement purposes even though it remains technically conditional until opening inspection.

Critical Path Analysis

Parallel Work Stream Execution Map for a 21-Day Compressor Overhaul

The defining characteristic of a major rotating equipment overhaul is that it creates multiple parallel work streams that must converge at precise points in time for the overhaul to stay on the critical path. Unlike static equipment work where activities are largely sequential, a compressor overhaul simultaneously involves on-site mechanical disassembly and reassembly, off-site vendor shop work on the rotor, separate electrical motor overhaul, and instrumentation recalibration, all of which must synchronize for the machine to be reassembled and tested on schedule. The following execution map shows how these parallel streams overlap across a 21-day turnaround window, with the critical path highlighted by the sequence of dependencies between streams.

Mechanical Vendor Shop Electrical Instrumentation Testing
Disassembly and Initial Inspection
D1-D6
Vendor Shop Rotor Overhaul

D5-D16
Electrical Motor Overhaul

D3-D12
Bearing and Seal Preparation

D8-D14
Reassembly with New Components

D15-D19
Instrumentation Recalibration

D16-D19
Alignment and Coupling

D19-D20
Dynamic Testing and Commissioning

D20-D21

The critical path in this example runs through disassembly, vendor shop rotor overhaul, and reassembly, with the vendor shop segment being the longest single activity at 12 days. If the vendor shop delivers the rotor even one day late, the entire reassembly sequence shifts and the testing window compresses, creating risk that the machine will not be fully tested before the unit startup deadline. This is why vendor shop progress monitoring during execution is not an administrative task but a critical path management activity that should receive the same level of daily attention as on-site mechanical work. iFactory tracks vendor shop milestones alongside on-site progress in a single view, ensuring that off-site delays are visible to the entire turnaround team in real time.

Vendor Coordination

Vendor Dependency Scorecards for Overhaul Execution

Vendor coordination during rotating equipment overhauls is fundamentally different from vendor management for static equipment work because the vendor is not just providing a service on your site but is actively performing work at their facility that directly controls your critical path. This creates a dependency relationship where your schedule is held hostage by the vendor's shop capacity, workforce availability, and parts supply chain. The following scorecards define the five critical vendor roles in a major rotating equipment overhaul, what each vendor needs from your facility to begin and complete their work, and the schedule risk they introduce if their dependencies are not managed proactively.

Rotor Overhaul Shop
Key DeliverablesMachined rotor with certified dimensional report, balance certificate, NDE results
Needs From FacilityRotor delivered by D4, historical run data, manufacturer drawings, specified clearances
Shop Duration8-14 days depending on scope
Schedule RiskHigh - Directly on critical path
Dry Gas Seal Vendor
Key DeliverablesNew or refurbished seal assemblies, installation supervision, leakage test certification
Needs From FacilitySeal cavity dimensions confirmed at opening, process gas composition data, barrier gas supply
Site Duration2-4 days for installation and testing
Schedule RiskHigh - Must align with reassembly
Electrical Motor Service
Key DeliverablesRewound or refurbished stator, tested rotor, new bearings, updated test certificates
Needs From FacilityMotor delivered to shop by D3, winding data, test voltage specifications
Shop Duration7-12 days depending on rewind requirement
Schedule RiskModerate - Parallel to rotor, must return before alignment
NDE Inspection Service
Key DeliverablesMagnetic particle, dye penetrant, and ultrasonic inspection reports with certified results
Needs From FacilityComponent access within 48 hours of opening, cleaned surfaces, lighting and power
Site Duration1-3 days depending on findings and scope expansion
Schedule RiskModerate - Findings can expand scope
Alignment and Vibration Specialist
Key DeliverablesLaser alignment report, baseline vibration signatures at all operating speeds, trim balance report
Needs From FacilityMachine reassembled and coupled, temporary piping disconnected, tag-out confirmed
Site Duration1-2 days for alignment and vibration testing
Schedule RiskLow - Late in schedule but short duration

The critical coordination failure mode is not vendors failing to perform their technical work but vendors being unable to start their work because the facility has not delivered the components, data, or site access they need on the date specified in the contract. Every day a vendor waits for a rotor delivery or dimension confirmation is a day added to the critical path that cannot be recovered. Proactive vendor dependency management means treating the vendor's input requirements as internal work packages with the same priority and tracking rigor as any on-site activity.

Decision Framework

Repair Versus Replace Decision Matrix for Overhaul Scope

One of the most consequential decisions during any rotating equipment overhaul is whether to repair a damaged component or replace it with a new or refurbished unit. This decision affects cost, schedule, and future reliability, and it is often made under time pressure during execution when the component is open and inspected for the first time. Having a pre-defined decision framework eliminates the ad-hoc deliberation that consumes valuable execution time and ensures that decisions are consistent with the organization's risk tolerance and long-term asset strategy. The following matrix provides the decision criteria and scoring guidance for the most common repair-versus-replace decisions encountered during centrifugal compressor overhauls.

Component Repair Option Replace Option Decision Criteria Recommended Threshold
Rotor Shaft Shop machining to remove scoring, plating of worn journals, re-balancing New shaft from manufacturer or certified aftermarket supplier Remaining dimensional margin after machining, number of previous repairs, criticality of shaft as single-point failure Replace if machining removes more than 10% of original diameter or if this is the second repair on the same shaft
Impeller Weld repair of erosion damage, re-machining of blade profiles, re-balancing New impeller from OEM or reverse-engineered equivalent from certified foundry Extent of erosion or corrosion damage, number of affected blades, impact on aerodynamic performance, material weldability Replace if more than 15% of blade area is affected or if leading edge erosion exceeds 3mm depth on any blade
Dry Gas Seal Refurbish with new sealing faces and secondary seals by certified seal shop New seal assembly from OEM or approved alternative supplier Seal face condition, spiral groove wear depth, secondary seal degradation, hours since last refurbishment Replace if this is the third refurbishment cycle or if groove depth loss exceeds 25% of original specification
Thrust Bearing Re-babbitting of worn pads, re-machining of thrust collar, re-tinning New bearing assembly with pads and collar from OEM or certified bearing shop Babbitt thickness remaining, pad temperature history, thrust collar surface condition, alignment of pad pivots Replace if babbitt thickness is below 75% of original or if temperature history shows trending degradation over last two run cycles
Diaphragm Re-machining of sealing edges, weld repair of cracks, re-staking of vanes New diaphragm from OEM or certified fabrication shop Crack extent and location, vane attachment integrity, sealing edge wear, material condition after extended service Replace if cracks extend into vane attachment area or if re-machining would reduce wall thickness below minimum design allowance
Balance Drum Re-machining of balance surface, new balance seal rings, re-balancing New balance drum from OEM or certified machine shop Surface wear depth, remaining dimensional margin, balance seal clearance increase since last overhaul Replace if surface wear exceeds 2mm or if clearance increase suggests more than 50% of balance capacity has been lost

The most important principle in applying this matrix is that the thresholds should be reviewed and approved by the engineering authority before the turnaround begins, not debated in the field while the machine is open and the clock is running. Pre-approved decision thresholds, documented in the work package and signed off by the turnaround manager and rotating equipment engineer, allow the field supervisor to make repair-or-replace decisions immediately at the point of inspection without waiting for engineering review that could take hours or days and consume critical path time.

Recommissioning

Post-Overhaul Testing and Recommissioning Protocol

The recommissioning phase is where the value of the entire overhaul is either realized or lost. A machine that has been overhauled to the highest standards but is recommissioned improperly can sustain damage that negates the overhaul investment and potentially shortens the machine's remaining useful life. The following staged protocol defines the testing sequence from static verification through full-load operation, with each stage serving as a gate that must be passed before proceeding to the next. Skipping stages or combining stages to save time is the most common cause of post-overhaul failures in the first 30 days of operation.

S1
Static Verification and Electrical Checkout
Reassembly complete, all quality hold points signed off, alignment report accepted, coupling installed
Verify all bolt torques against specification, confirm proper installation of all seals and gaskets, megger test motor windings, verify control system inputs and outputs, confirm protection relay settings, check lube oil system piping integrity, verify seal gas system pressurization capability, confirm all instrumentation readings at zero-speed condition
All static checks pass, electrical insulation resistance above minimum specified value, all control system functions verified, lube oil system circulation established with no leaks
S2
Barring Speed Rotation
Stage 1 complete, turning gear engaged, lube oil at operating temperature and pressure
Run machine on turning gear for minimum 4 hours, monitor bearing temperatures during barring, check for any abnormal sounds or vibrations at low speed, verify lube oil flow to all bearings, confirm seal differential pressure is maintained, record initial vibration baseline at barring speed
Bearing temperatures stabilize within normal range, no abnormal sounds detected, lube oil flow confirmed at all bearing locations, seal gas differential pressure maintained
S3
Unloaded Speed Run
Stage 2 complete, process isolation valves closed or suction blanked, anti-surge valve fully open
Accelerate machine to minimum operating speed, hold at each critical speed for vibration observation, record vibration amplitude and phase at all bearing locations, monitor bearing temperatures during speed increase, verify overspeed trip function at specified setpoint, confirm axial displacement within acceptable limits, record thermal growth data
Vibration at all bearings below alarm limits at operating speed, bearing temperatures below alarm limits, axial displacement within design clearance, overspeed trip verified at correct setpoint
S4
Partial Load Operation
Stage 3 complete, process system ready to accept gas, all safety systems verified functional
Introduce process gas at minimum load condition, gradually increase load in specified increments, hold at each load point for minimum 30 minutes while recording all operating parameters, map vibration response across operating range, verify anti-surge control system response to manual perturbation, check seal leakage rates at operating pressure
Vibration remains below alarm limits at all load points, bearing temperatures stable and below alarm limits, seal leakage within specification, anti-surge system responds correctly to test perturbation
S5
Full Load Performance Verification
Stage 4 complete, machine stable at partial load for minimum 2 hours
Increase load to maximum operating point, record complete performance curve from minimum to maximum flow, compare actual head and efficiency against design curves and pre-overhaul baseline, verify that performance restoration meets the target established in the overhaul scope, conduct 24-hour continuous run at normal operating point to verify stability, record final vibration baseline for future condition monitoring reference
Performance curve within 3% of design or within 2% of pre-overhaul baseline whichever is applicable, all parameters stable during 24-hour run, final vibration baseline recorded and filed in condition monitoring system
Frequently Asked Questions

Common Questions About Rotating Equipment Overhaul Planning

How do we decide whether to use the OEM or a third-party shop for a major compressor rotor overhaul?

The OEM versus third-party shop decision depends on four factors: the machine's criticality and consequence of failure, the availability of manufacturer drawings and material specifications, the third-party shop's certified experience on your specific machine model, and any warranty or service agreement obligations that may require OEM work. For Tier 1 machines where failure would cause a total unit shutdown and extended production loss, OEM overhaul is typically justified despite the 20 to 40 percent cost premium because the OEM has access to original manufacturing data, proprietary repair procedures, and can provide warranty coverage that third-party shops cannot match. For Tier 2 machines where a quality third-party shop has documented experience on the specific model and can provide equivalent quality assurance, the cost savings often justify the third-party route. The key requirement regardless of shop selection is that the facility must provide complete manufacturer drawings and specifications to the third-party shop, as machining to incorrect dimensions will invalidate the overhaul regardless of the shop's technical competence. Book a demo to see how iFactory tracks vendor shop selection criteria and performance history.

What is the value of maintaining a spare rotor program and how do we justify the capital investment?

A spare rotor program eliminates the single most critical path dependency in a compressor overhaul by allowing the machine to be reassembled with a pre-overhauled spare rotor while the in-service rotor is at the vendor shop. This typically compresses the critical path by 8 to 14 days depending on the rotor overhaul scope, which on a large refinery unit represents 2 to 5 million dollars in avoided production revenue per day of schedule reduction. The capital investment for a spare rotor ranges from 500,000 to 2,000,000 dollars depending on machine size and complexity, but the investment is recovered in a single turnaround cycle if the spare rotor enables even two days of schedule compression. The secondary benefit is that the spare rotor can be overhauled proactively in the vendor shop before the turnaround begins, transferring shop schedule risk from the execution window to the planning window where delays have no production impact. For any compressor that is on the critical path of a turnaround and requires rotor removal, a spare rotor is one of the highest-return capital investments available in turnaround planning. Contact support for spare rotor ROI modeling tools.

How do we manage the risk of scope expansion when opening inspection reveals unexpected damage?

Scope expansion risk is managed through three complementary strategies applied during the planning phase rather than reacted to during execution. First, pre-procure high-probability conditional scope items based on a formal probability assessment conducted during the P2 scope definition phase. Any component with greater than 60 percent probability of requiring replacement based on condition monitoring trends, age, and service history should be procured and staged on-site before the turnaround begins. Second, negotiate pre-priced change order provisions with all critical vendors so that if scope expansion requires additional shop work, the pricing and duration impact are already agreed and the vendor can begin immediately without contract renegotiation. Third, maintain a dedicated contingency budget of 15 to 25 percent of the planned overhaul cost that is specifically reserved for conditional scope confirmation, separate from the general turnaround contingency. The most important discipline is to never treat conditional scope as a surprise that requires emergency response. It is a predicted probability that should be pre-planned, pre-procured, and pre-budgeted to the maximum extent possible. Book a demo to explore conditional scope management tools.

What are the most common causes of schedule delay in rotating equipment overhauls and how can they be prevented?

Analysis of over 150 rotating equipment overhaul delays across refinery and petrochemical turnarounds identifies five recurring causes that collectively account for 80 percent of all schedule delays. Late rotor delivery from the vendor shop is the single largest cause at 28 percent, almost always driven by the facility failing to deliver the rotor to the shop on the contractually specified date, which cascades through the shop schedule. Missing or incorrect spare parts is the second cause at 22 percent, where parts staged on-site do not match the actual components found at opening due to drawing revision changes or incorrect bill of materials. Unexpected scope expansion from opening inspection findings that were not anticipated in the conditional scope assessment accounts for 15 percent of delays. Vendor specialist unavailability, where the seal vendor or alignment specialist cannot mobilize when needed because their schedule was not confirmed with a firm commitment, causes 10 percent of delays. The remaining 5 percent is attributed to crane and rigging conflicts where heavy lift scheduling conflicts with other turnaround activities. Every one of these causes is preventable through disciplined planning and proactive dependency management. Contact support for turnaround delay prevention strategies.

How does iFactory specifically support rotating equipment overhaul tracking during turnaround execution?

iFactory provides dedicated rotating equipment overhaul tracking within the turnaround command center that integrates on-site mechanical progress, off-site vendor shop milestones, electrical motor overhaul status, and instrumentation recalibration activities into a single real-time view. The platform maintains a digital twin of each machine's overhaul plan with the original baseline schedule, and automatically highlights deviations from the plan as they occur. Vendor shop progress is tracked through mandatory milestone reporting that the vendor submits through the platform, triggering alerts if any milestone is missed or at risk. Parts staging verification is tracked against the bill of materials with confirmed-on-site status for each component. The critical path impact of any delay in any work stream is automatically calculated and displayed, allowing the turnaround manager to see immediately whether a vendor delay or a parts shortage will affect the overall turnaround end date. Post-overhaul, all testing data from the recommissioning protocol is captured in the platform and linked to the machine's asset record for future condition monitoring reference. Book a demo to see the rotating equipment overhaul dashboard in action.


Compressors / Turbines / Pumps / Motors / Vendors / Testing

Your Most Expensive Machines Deserve More Than a Spreadsheet to Track Their Overhaul.

iFactory gives your turnaround team the real-time visibility into every rotating equipment work stream, vendor dependency, and testing stage needed to bring your compressors, turbines, and pumps back online on schedule and verified for reliable operation.


Share This Story, Choose Your Platform!