Pump Inspection Checklist: Weekly Centrifugal Pump Check

By James Smith on November 27, 2026

pump-inspection-checklist

A pump inspection checklist is only as good as the limits written on it. An item that only says "check bearing temperature" leaves each technician to invent a number; an item that says "below 70 °C and within 10 °C of last week" lets two people reach the same answer. The ready Centrifugal pump weekly check in iFactory Inspection is written that way, item by item. This page covers the 14 items, the limits that matter most, the order of the round, what a failed item sets in motion — using our test round on boiler feed pump P-101 — and where the checklist stops. Run the pump check in your own workspace once your company is set up.

Inspection · Pump checklist

Weekly centrifugal pump check: 14 items, each with its limit

A technician round of about 15 minutes, once a week. Each of the 14 items says how to check it and what counts as a pass, so the same pump is judged the same way every week.

14 items About 15 min, weekly One lockout step Work order on failure
Photograph of the topic with the title Weekly centrifugal pump check: 14 items, each with its limit

The weekly pump check at a glance

The ready checklist is the weekly centrifugal pump check: 14 items, about 15 minutes, done by a technician. The items are grouped into five sections so the walk around the pump has a fixed order, and one of them — the coupling insert and hubs — is flagged as a lockout step.

14Items
15 minTechnician, weekly
5Sections
1Lockout step

The five sections are Safety, Mechanical, Lubrication, Instruments and Electrical. Mechanical is the longest group. The coupling check is the lockout step: the pump is locked out and the guard comes off before anyone looks at the insert and hubs.

Check the pump the same way every week

Do the same 14 items in the same order every week. Several limits compare this week's reading with last week's, or with the normal value on the tag, so a slow change is caught as well as a reading that is already over the line.

Six limits that carry the check

These six items are the ones technicians ask about most. Each limit is written into the item itself, with how to take the reading and what passes, so the person on the round is not guessing.

1

Bearing temperature

Take an infrared reading on the drive-end bearing housing after the pump has been running for 30 minutes, and a second reading on the pump-end housing.

Both pass below 70 °C and within 10 °C of last week's reading. A bearing that is still under 70 °C but has risen by more than 10 °C fails, because the change itself is the warning.

2

Vibration

Place a vibration pen on each bearing housing, across and up, on both the pump and the motor.

A reading below 4.5 mm/s passes. Above 7.1 mm/s the item says to report it at once, not only to mark it Failed. These are the general figures in the ready checklist; change them if your pump's manual gives a different value.

3

Mechanical seal

Shine a torch on the seal gland and on the drain beneath it, and look for wet marks or a running leak.

A seal that is dry, or that loses less than one drop a minute, passes. A steady drip or a spray fails, and the item is High priority, so the work order is due in 24 hours.

4

Suction strainer

Read the suction gauge and compare the pressure drop with last week's reading, or with the value written on the tag if that is what your site uses.

A drop under 0.3 bar, or under the tag value, passes. A higher drop means the strainer is clogging and should be cleaned. Write the figures in the note if the item fails, because the app records OK or Failed, not the number.

5

Discharge pressure

Read the discharge gauge while the pump is on duty, and compare it with the normal reading written on the tag.

The item passes when the pressure is within ±10% of that normal value and the needle is steady. A swinging needle, or a reading outside the band, fails. The comparison only works if the normal value is on the tag for the next person to see.

6

Running current

Read the running current from the ammeter or the drive display — do not open live panels to take the reading.

The current should be at or below the nameplate full-load amps, and within 10% of the normal reading for that pump. A high current on the same visit as a hot bearing or a noisy casing is worth writing into the note together.

Limits in the ready library are written in °C and bar, and the app shows them in your organisation's units. They are general values. Check each one against the pump's manual and edit the item if your figure is different.

When the seal item fails

In our test round, item 8 — the mechanical seal — was marked Failed with the note "Seal drip at pump gland, approx 1 drop/10 s". That rate is a steady drip, so it fails the written limit (dry, or less than one drop a minute). The round raised work order WO-0002 for P-101 at High priority, with the how-it-is-checked text attached, so the fitter sees the limit and the note together rather than a bare failure flag.

Finding WO-0002, New: seal drip at pump gland on P-101, with Start work, Assign, Waiting on, Mark done and Cancel, and the how-it-is-checked text
Finding WO-0002 raised from the failed seal item, QA account test data.

Priority sets the due time

The mechanical seal item is High priority, so a failure raises a work order due in 24 hours. Urgent items are due in four hours, Medium in 72 hours and Low in 14 days.

Note is required

A failed item cannot be saved until the technician writes a note. That note travels with the work order, which is why the drip rate and the location belong in it, not only the word Failed.

Record keeps it

The round record keeps item 8 as Failed, with the note, the how-it-is-checked line and the limit, so anyone opening the record later can see what was found and what the item required.

Where the pump checklist stops

The weekly centrifugal pump check is a walk-round with written pass and fail lines, not a continuous condition-monitoring system. Knowing where it stops helps you use it for what it is good at, and not for what it cannot do.

No numeric readings

Results are recorded as OK, Failed or N/A. The technician judges the reading against the written limit, but the app does not store the number itself. If you want the value later, write it in the note when the item fails.

Centrifugal pumps

The ready list is written for a centrifugal pump. Fire pumps, sewage pumps and other types are different equipment, with different items and limits, so edit this list or draft your own rather than forcing those machines through it.

Your OEM manual rules

The temperatures, vibration figures and pressure drops in the ready items are general. If the manufacturer gives a different limit for your pump, change the item to that figure before you start the weekly rounds.

Doing the round in a sensible order

The 14 items are grouped so a technician can walk the pump once instead of circling it for each check. Start with the two Safety items while the pump is running: the coupling guard, which should have every bolt in, no gaps, and nothing touching the coupling, and the floor around the base, which should be free of water, oil, hoses and tools.

Then stop and lock the pump out for the coupling insert and hubs. A pass is an insert that is not cracked or missing pieces, no rubber dust, and hubs tight on the shafts. Put the guard back before you release the lockout. Once the pump is running again, finish the Mechanical group: both bearing temperatures, vibration, casing noise, the mechanical seal, and the hold-down bolts, which you try with a spanner and which fail if any are loose or the baseplate or grout is cracked. A steady hum at the casing passes; a gravel sound points to cavitation, and a squeal or grinding to the bearings.

Lubrication, Instruments and Electrical come last. Read the bearing oil at the sight glass or oiler — level at the mark, oil clear amber, not milky and with no metal flakes — then the discharge gauge, the suction strainer drop and the motor current, and look at the motor cable and terminal box without opening it live. The lid should be on with every screw, the gland tight, and the insulation undamaged. Done in this order, the round takes about 15 minutes.

Why several items compare with last week

Both bearing temperatures pass below 70 °C and also within 10 °C of last week's reading. The second condition matters because a bearing that has crept from 52 to 68 °C still passes the absolute limit and is already telling you something is changing. Discharge pressure works the same way: it passes within ±10% of the normal reading on the tag, with a needle that is steady rather than swinging.

The suction strainer item likewise compares this week's drop with the last reading, or with the value on the tag. The app does not store a number for these readings, so the comparison depends on a record the next person can use. Write last week's figure in the note, or the normal value on a tag at the pump. When an item fails, that note is what the work order carries, together with the how-it-is-checked line and the written limit.

Frequently asked questions

What is on the ready centrifugal pump checklist?

It has 14 items in five sections: Safety (coupling guard and floor), Mechanical (coupling insert and hubs, both bearing temperatures, vibration, casing noise, the seal and hold-down bolts), Lubrication, Instruments and Electrical. Each item has a how-to-check line and a written pass or fail limit.

How long does the weekly pump check take?

The ready checklist is a technician round of about 15 minutes, done once a week. That timing holds if the items are done in section order, the pump is already running for the temperature and vibration readings, and time is allowed for the coupling lockout in the same visit.

Which pump items need the pump locked out?

Only one item is flagged for lockout: the coupling insert and hubs. The pump is locked out and the guard comes off; a pass is an insert that is not cracked or missing pieces, no rubber dust, and hubs tight on the shafts. The coupling guard itself is a separate Safety item, checked with the pump running.

Can I change the limits?

Yes. The how-to-check line, the pass or fail wording and the frequency can all be edited before you save the checklist, so your pump's manual can replace the general figures in the ready list. Weekly rounds then use your wording, and a work order from a failure will quote the limit you wrote.

What happens when an item fails?

A failed item cannot be saved without a note, and a photo can be added too. A work order is then raised with the item's priority, the note, the how-it-is-checked line and the limit. High items such as the seal are due in 24 hours. The finding is listed on the Findings tab — see inspection findings tracking.

What counts as a failing seal, and what vibration limit is used?

On the seal, dry or less than one drop a minute passes; a steady drip or a spray fails. On vibration, a pen reading below 4.5 mm/s passes, and above 7.1 mm/s the item says to report it at once. Both are High items, due in 24 hours, and both figures should be checked against your pump's manual.

Put the weekly pump check on every pump

Choose the ready centrifugal pump checklist, assign it to the pumps you want covered, and the weekly rounds appear for the technician or role you name when you save it.

  • 14 items, each with a how-to-check line and a written pass or fail limit
  • The coupling insert and hubs step is flagged for lockout, so it is not done with the guard off on a running pump
  • A failed item raises a work order that carries the priority, the note and the limit

14-day free trial · no card needed

Photograph supporting the topic: Put the weekly pump check on every pump