What Is OEE? How Line OEE Calculates It

By James Smith on November 20, 2026

what-is-oee-and-how-it-is-calculated

OEE, overall equipment effectiveness, says how much of a line's planned time went into good product. Line OEE calculates it as availability × performance × quality from the line's own records: shift time, stops with their reasons, the ideal cycle and good and rejected units. Breaks and planned stops never count against the line, minor stops count against speed, and other stops count against uptime. You can sign up to access Line OEE and see the calculation on your own line, with 14 days of Pro features and no card.

iFactory Tools · Production · OEE method

What is OEE, and how Line OEE calculates it

Availability × performance × quality, from planned time down to good units, using the line's own records.

A × P × QFrom planned time to good units
AvailabilityPerformanceQualityWorld class 85 %
OEE · one line, one shift
Availability
Performance
Quality
Breaks and planned stopsNot a loss
Minor stopsSpeed
Other unplanned stopsUptime

The formula

Line OEE follows the ISO 22400 definitions, according to the code, and calculates each part from records the line already keeps.

Availabilityrun ÷ planned×Performanceideal cycle × units ÷ run×Qualitygood ÷ all units=OEEshare of planned time as good product

Each step, exactly as calculated

TermHow Line OEE works it out
Planned timeShift time less planned breaks and planned stops
Run timePlanned time less unplanned stops: breakdowns, changeovers and setups, waiting for material, quality holds, and stops not yet explained
AvailabilityRun time ÷ planned time
PerformanceIdeal cycle × units made ÷ run time, capped at 100 %
QualityGood units ÷ (good + rejected units)
OEEAvailability × performance × quality

The world-class reference, worked through

90 %availability
95 %performance
99.9 %quality
≈ 85 %OEE, the world-class line

Line OEE shows 85 % as the world-class reference on each line card. Each line also has its own target OEE, set in Setup, and that is what alerts and Hour by hour use.

Set the line
Count the units
Read the OEE

See OEE calculated from your own line

Counted by camera or entered by hand, the same calculation runs. 14 days of Pro features, no card.

Every stop reason knows its loss

Each stop reason is mapped to a category. Breakdowns, changeovers, waiting for material, no operator and quality holds take availability; jams and minor stops take performance; planned breaks and meetings are planned and not a loss.

Stop reasons settings where each reason is mapped to a category that takes availability, takes performance or is planned and not a loss
Each stop reason says which part of OEE it takes. Sample data from a test account, not customer results.

Rules that keep the number honest

Overlapping stops count once

If two machines on a line are down at the same time, that time is lost once, not twice.

Open stops count up to now

A stop still going, or a line gone quiet with no stop written yet, counts as stopped time until it ends.

No production, not 100 %

Planned time with zero units shows as No production, not a misleading figure.

Performance is capped at 100 %

If the ideal cycle is set too slow, performance stops at 100 %, so check each line's normal speed.

The same number as a waterfall

On the Analysis page, the calculation is drawn from planned time down to fully productive time. Fully productive time ÷ planned time is the OEE.

Where the time went waterfall from planned time to fully productive time
The same calculation on the Analysis page, from planned time down to fully productive time. Sample data from a test account, not customer results.

Expert review

A close review of the OEE code in the product repository shows the standard definition applied with care: planned stops removed first, minor stops kept as a speed loss, overlaps counted once and a No production state instead of a false 100 %.

One caution: performance is capped at 100 %, so an ideal cycle set too slow is hidden rather than flagged. Set each line's normal speed from a real best run.

Frequently asked questions

What does OEE stand for?

Overall equipment effectiveness. It says how much of a line's planned time went into good product, as availability × performance × quality.

Do breaks and planned stops lower OEE?

No. Planned breaks and planned stops such as meetings come out of planned time, so they never count against the line. Unplanned stops lower availability.

Why do minor stops lower performance and not availability?

Minor stops stay inside run time, so they show as lost speed, following the usual TPM convention. Breakdowns, changeovers, waiting for material and quality holds take availability. You can sign up to access Line OEE and see how your own reasons are mapped.

What is world-class OEE?

Line OEE uses 85 % as its world-class reference: 90 % availability × 95 % performance × 99.9 % quality. Each line also has its own target OEE, set in Setup.

What does Line OEE show when a line made nothing?

When there was planned time but no units, Line OEE shows No production instead of a misleading figure. You can get started with Line OEE and check the calculation on one line.

Calculate OEE from your own line

Set one line with its shifts, normal speed and stop reasons, and Line OEE does the arithmetic.

  • Availability, performance and quality
  • Stop reasons mapped to losses
  • Waterfall from planned to productive time

Free for 14 days · no card needed

Where each loss goesLine OEE method
A × P × Q
LossAvail.Perf.Quality
Breakdown, changeover
Jam or minor stop
Rejected units
Sample layout, not customer resultsISO 22400